Once again, a huge thanks to the DPR team for their tireless efforts throughout December, moving the project forward while managing a great deal of rain and nearly 8 million gallons of water. The project is now 27% complete!

The winter break provided an ideal window for our team to conduct work on the joint conditions connecting the Lulu’s Place campus with our neighbors at St. Bernard High School. We are so thankful for their continued collaboration.

On the east side of campus, the final concrete pour at the Welcome Center was completed just ahead of the late-December rains. In addition, masonry work began on both Tennis Pavilions, adding visible vertical elements to the site. On the west side, much of the aggregate base material was installed on our soccer fields, and new trees were planted. Stay tuned for an upcoming update on the installation of our Musco sports lighting!