Despite a full day of rain recently, the construction team continues to make great strides across the 34-acre campus. With rough grading complete, crews are now installing key underground infrastructure, including utilities and storm drains, in advance of the winter months.

In Area 1, irrigation work is in progress, concrete is being poured for the Restroom, and planting of the first trees will soon bring new life to the Dog Park, Soccer Fields, and Paseo. In Areas 2 and 3, foundations are taking shape for the TGR Learning Lab and Welcome Center, and preparations for the footings at both Tennis Pavilions are underway.